Acabado

Well .. the end is here. The crew will be finished this week with their part. The casa is finished on the exterior. So now it is up to us to finish the interior.It took us 3 months longer than expected, but when you consider that everything is done by hand, we are okay with that.

Budget wise, it was $45.00 usd  a SQ foot and we got many extras that we were not expecting. For that price they included a lower concrete patio and a concrete ramp to the garage and stairs. We did have them paint the three tall sides for us, and all Ismael wanted for this, was a trade of some items that cost about $250.00.

So what we learned, is to be patient. Because everything is done by hand it takes longer and yes you can build in Mexico without having to be on site the whole time.

For a video(if I figure out how to load it) visit our facebook page Casa de los suenos .

1918111_10204340239504802_9196684328023523489_n032016

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s